When a buyer requests a configuration change after packaging is already in production, someone is going to absorb the cost of scrapped materials. This post walks through a real case — a mid-order kit change that made 600 printed packaging sets unusable — and explains how we handled the cost-sharing conversation, and what buyers can do to prevent this situation from the start.
Where Things Started to Go Wrong
The original order was straightforward: we manufacture the bare tool, pack it according to bare-tool dimensions, and ship. The customer supplies the packaging artwork; we produce the boxes to match.
Everything moved smoothly. Materials were ready, the printed colour boxes and outer cartons were already in the warehouse. We were one step away from starting the packing line.
Then the customer sent a message. They had changed their plans: they wanted to ship a kit — tool, battery pack, and charger together. They would source the battery and charger themselves, ship them to us, and we would pack everything as a set.

When that message came in, the whole team felt it immediately.
Because it meant one unavoidable thing: the boxes we had already printed — sized for the bare tool — could not fit the battery pack and charger. All 600 sets of colour boxes and outer cartons were now unusable.

Our First Move: Test Before Saying No
When the change request came through, we did not immediately tell the customer the packaging could not be used. Instead, we ran a round of practical tests first.
We tried several approaches: repositioning the product inside the box, reducing the insert thickness, adjusting the pack quantity per carton. The conclusion after testing: none of it was viable. Forcing the kit into the original box would create a high risk of compression damage in transit — the customer would receive deformed packaging.

Want to understand how our production process is structured before reading on? → See our manufacturing process
This step took time we did not have to spare. But we felt it was necessary.
If we had simply told the customer the boxes would not work, they might reasonably wonder whether we had actually checked — or were just looking to avoid the problem. With test results in hand, our position was backed by evidence, and the customer could see we had genuinely tried to make it work.
We Came to the Customer With a Solution, Not a Problem
Once testing was complete, we put together a concrete proposal rather than waiting for the customer to decide what to do:
- Re-measure the kit configuration and confirm the dimensions needed for new packaging

- Identify a printer that could turn around an urgent order, and move immediately to layout, proofing, approval, and print

- On the 600 unusable packaging sets: we proposed splitting the loss 50/50 — we absorb half, the customer absorbs half

The cost-sharing proposal was something we discussed internally before presenting it. Objectively, the configuration change was entirely the customer’s decision. The packaging was a finished product, already in stock. The full loss should arguably have sat with the buyer.
But this was a first order with a buyer who had expressed interest in a long-term relationship. Our judgment was that fighting hard over the full cost at this stage carried a bigger risk: damaging the relationship before it had a chance to develop. Splitting the loss was the outcome we felt was fair given the circumstances.
The customer agreed. The replacement packaging was completed on an expedited timeline. The order shipped on schedule.
What We Think Importers Should Know
After working through this case, we reflected on what it means from the buyer side. A few things stood out as genuinely worth knowing — not just for this situation, but for any order that involves custom packaging.
Once printing starts, packaging specifications are locked
This is something many buyers are not fully aware of. Once layout is finalised and printing begins, dimensions, material, and structure are fixed. There is no way to modify them — only to scrap and restart.
As a general guideline: once packaging proofs have been approved, the configuration should not change. That approval typically happens three to four weeks before production begins. Any change request after that point does not reflect a lack of flexibility on the factory side — it reflects the physical reality of how print production works.
Before making a change, ask the factory what it means right now
Changes are not always avoidable. But before requesting one, it is worth asking the factory directly: what materials have already been ordered? What has already been produced? What would a change at this stage cost in time and money? → See our manufacturing process
We have that information on hand at every stage of an order. But we do not always volunteer it unprompted — partly because we are often waiting for a clear direction from the buyer before we know whether a change is actually happening. If you ask, we can give you a straightforward assessment of the impact.
On first orders especially: get the configuration confirmed in writing
We have managed a large number of first orders over the years. The pattern we see consistently is that first orders carry a higher risk of mid-process issues than repeat orders — not because either side is less careful, but because both sides are still learning how the other works. Confirmation processes are less established, and it is easier for assumptions to go unverified.
Our standard practice now is to do a written configuration freeze before the first order goes into production: product model, voltage spec, included accessories, packaging format — all confirmed line by line, in writing.
This is not about distrust. It is about giving both sides a clear record. If something does go wrong later, everyone is working from the same documented baseline — which makes resolution much faster and much less contentious.
If a loss has already occurred, bring documentation to the conversation
If a mid-order change has resulted in scrapped materials or rework costs, ask the factory to provide documentation of what was already produced and what the costs are. Do not accept verbal estimates — the numbers need to be traceable.
It is also worth thinking clearly about responsibility: who initiated the change? Did the factory fulfil its confirmation obligations before production started? When the responsibility picture is clear, cost-sharing conversations are much more likely to reach a practical outcome rather than becoming an argument.
A Final Note
We have always believed that order management work is not just about tracking milestones and chasing deadlines. In many cases, our team sits in the middle of an information gap between the buyer and the production process — and what happens in that gap has real consequences for both sides.
We hope that sharing cases like this one helps importers build a clearer picture of how production actually works at the execution level — not so factories can make a stronger case for themselves, but so buyers can make better-informed decisions at the moments that matter: when placing an order, when confirming a spec, and when a change comes up.
If you are preparing a first power tool order and want to talk through the process, or if you have run into a situation like this one, feel free to reach out directly.